Guangxi Communications Investment Group accelerates delivery of multiple transport schemes

According to Guangxi Communications Investment Group Co., Ltd, published on 10 November 2026, the group presses ahead with transport infrastructure works under the principles of safety, environmental protection, mature technology, cost efficiency and long-term structural quality. All construction schedules stay on track, with teams prioritising key milestones in the fourth quarter.

In October, the shared section expansion project of the Yulin–Liping Expressway completed the laying of the lower asphalt course across its full route, marking a major breakthrough for the main pavement works. Pavement works on the southern section of the Wuzhou Ring Expressway entered large-scale laying of the upper asphalt course. Both the Yulin–Liping shared section expansion and the southern Wuzhou Ring Expressway are due to open to traffic within the year.

Ongoing expressway projects have recorded steady progress. Subgrade and lower bridge works for the Baise section of the Nanning–Baise upgrade on the G80 Kunming–Guangzhou Expressway are more than 70 per cent complete, and construction on the Nanning section has formally commenced. The arch rib of the Hongshui River Grand Bridge on the Leye–Wangmo Expressway has been closed, clearing a critical control point. Works on the Guilin–Zhongshan and Luocheng–Yizhou Expressways continue on site. Eight expressway schemes including the Pingtang–Tian’e Expressway have passed final acceptance.

78.png

Static acceptance for the Yulin North–Cenxi East section of the Nanning–Zhuhai High-speed Railway was finished in late August, and commissioning and testing have begun. Teams carry out dynamic inspections and safety checks ahead of opening. Tunnel and bridge works advance on the Cenxi East–provincial boundary section, and the 2,466.76-metre Dahua Tunnel has been broken through.

For the Huangtong–Baise Railway, a landmark scheme of the New Western Land-Sea Corridor, 23 out of 33 new tunnels in the Guangxi section have been safely broken through, with tunnel works standing at 77 per cent completion. Subgrade and tunnel works on the Liuzhou–Wuzhou Railway are fully finished, bridge works reach 99.6 per cent and track laying 91.13 per cent. Static acceptance has been completed for all six new station buildings, and dynamic testing for the whole line is scheduled to start in late November. Pile foundation works for bridges on the Guangxi stretch of the Hepu–Zhanjiang High-speed Railway stand at 94 per cent, and an intelligent prefabricated component yard has gone into full operation.

Digital transformation rolls out across expressway and railway sites. New construction techniques, equipment and smart site management are widely adopted, with 32 intelligent processes, new technology applications and micro-innovation outcomes compiled. Low-carbon construction trials including zero-carbon service areas and recycled aggregate reuse deliver practical results. Several projects have won national and provincial awards. Pingnan Third Bridge received the Zhan Tianyou Award for China Civil Engineering, the Leye–Baise Expressway took the National Quality Engineering Award, and the Tian’e Longtan Grand Bridge secured the Special Prize of the Guangxi Science and Technology Progress Award. Two subsidiaries have been shortlisted for the seventh Guangxi Zhuang Autonomous Region Chairman’s Quality Award.

The group will maintain delivery targets, adjust construction timetables and deploy resources to complete its annual work programme.